Prepare the following points before the installation date to avoid delays.

  • Two people. The installation is carried out by at least two people, as required by occupational safety regulations.
  • Pallet truck. A professional pallet truck is available. The components are too heavy to move to the installation site any other way.
  • Access. Every component can be reached with the pallet truck. Stairs, thresholds and narrow passages have been taken into account.
  • T13 power outlet. A free T13 outlet (230 V, single phase) is available at the installation location to supply the modual Core.
  • Grid connection prepared (400 V AC, 3-pole MCB, see below).
  • RJ45 LAN connection for the internet connection is available at the installation location.
  • Equipotential bonding prepared for the entire system, with a 6 mm² earthing conductor.
  • EMS or energy meter (optional) prepared, for example Solar Manager or an energy meter, connected via RS485.
Installation Circuit breaker
Without PV MCB C 20 A, 3-pole, 400 V AC
With PV MCB C up to 32 A, 3-pole, 400 V AC

The components have a high net weight.

  • Transport them only in the upright position.
  • Do not tilt them or lean them against anything.
  • Use suitable lifting and transport equipment.

Installation instructions for the Series Pro: site preparation checklist

Bring the installation material for the outlet and connections, the tools and the personal protective equipment described in Safety and warnings.